Douglas Avenue is fully open. Crane arrives Tue, Sep 8 · first lane impact Tue, Oct 20 · all lanes restored by Wed, Nov 11
Schedule current as of September 4, 2026 · this page is updated weekly during construction

Construction Update · Fall 2026

Downtown parking is going up.
Here's what it means for Douglas Avenue.

From late August through late October 2026, crews will erect the precast concrete structure of the Douglas Parking Center at 968 Douglas Avenue. Most of the work happens entirely on our property — the first six weeks — from crane arrival on September 8 through October 19 — require no road or lane closure of any kind. This page lays out every phase, the current target dates from our precast and construction team, and exactly what to expect on the road.

Rendering of the completed Douglas Parking Center at dusk, seen from the southeast corner with lit storefronts and the neon parking sign

The finished Douglas Parking Center — southeast corner at dusk

Sep 8 – Nov 10
Full erection window — crane assembly Sep 8–9, erection Sep 10 – Nov 5. No road impact until October 20
Oct 20 – Nov 5
Single-lane flagging on Douglas Ave. — about thirteen working days, beginning after the Art & Craft festival weekend
Nov 9 – 10
The only full closure — Monday and Tuesday, the quietest downtown days. Both lanes reopen by Wednesday, Nov 11

Phase by phase

The Construction Timeline

The dates below are from the Hawkins Construction precast erection schedule dated September 3, 2026, incorporating Metromont delivery dates, — the current working schedule for the job. If weather or logistics move a closure date, this page is updated and the City of Dunedin is notified before any closure begins.

No road or lane closure

Tue Sep 8 – Wed Sep 9, 2026 · 2 days

Crane Mobilization & Assembly

The erection crane moves to the job site and is assembled entirely within the property. Certified flaggers at the site entrance will briefly hold traffic only while a truck is actually turning in or out. Both lanes of Douglas Avenue stay open.

No road or lane closure

Thu Sep 10 – Mon Oct 19, 2026 · about 6 weeks

West & Center Bays — North to South

Erection begins September 10, building the West and Center bays — the two farthest from the road — north to south. The crane and all delivery trucks operate inside the property limits — both lanes of Douglas Avenue remain open for this entire stretch, the longest phase of the job. All work runs Monday through Friday — no weekend activity, and no precast deliveries on Saturdays or Sundays at any point in the program.

Single-lane flagging operation

Tue Oct 20 – Thu Nov 5, 2026 · about 13 working days

East Bay (Douglas Frontage) — North to South

The final bay sits along Douglas Avenue, so the crane needs the near lane. Barricades shift out to close one lane, and traffic alternates through the remaining 11-foot lane under certified flaggers — the road stays open in both directions, with brief waits during active picks, deliveries, and concrete pours. The closure runs about thirteen working days, Monday through Friday only — beginning the week after the Art & Craft festival weekend of October 10–11, which sees no construction activity, delivery traffic, or lane closure of any kind — and the lane is restored as soon as the frontage bay is complete. Work zone speed is 15 MPH, the sidewalk on the project side closes with marked crossings to the east side, and all deliveries end by 3:00 PM daily.

Full closure — two days

Mon Nov 9 – Tue Nov 10, 2026

Crane Demobilization

Taking the crane down requires the full width of Douglas Avenue for public safety — the only full closure of the entire project, scheduled for two days midweek. A signed detour routes traffic via Skinner Blvd., Broadway, and Main Street (see map below), pedestrian routing is maintained, and emergency services are coordinated in advance. In coordination with the City, it is deliberately placed on Monday and Tuesday — the quietest downtown days — avoiding Fridays and weekends entirely, with both lanes fully reopened by Wednesday morning, November 11. Douglas is fully open with no lane restrictions the Friday and weekend beforehand.

Tue Nov 10, 2026 — Precast erection complete · All lanes restored by Wednesday, Nov 11

Mark your calendar

The Two Traffic Impacts to Know

Out of the entire operation, only two windows touch traffic on Douglas Avenue — and during the first one, the road never fully closes. Here’s each in plain terms, based on the draft traffic control plans prepared by Spartan Safety Services (pending City of Dunedin approval).

Oct 20 – Nov 5

Single-Lane Flagging · ~13 Working Days

  • About thirteen working days, Monday–Friday only — begins Oct 20, after the Art & Craft festival weekend (Oct 10–11), which sees no construction activity at all
  • One lane of Douglas Ave. closes at the site; traffic alternates both directions through the open 11-ft lane under certified flaggers
  • Active during deliveries, crane picks, and concrete pours — expect brief waits, not a closed road
  • Work zone speed limit 15 MPH · work hours 7:00 AM – 5:00 PM · deliveries end by 3:00 PM · never on weekends
  • Sidewalk on the project side closed — signed crossings route walkers to the east sidewalk
  • Access to adjacent homes and businesses maintained throughout

Nov 9 – 10

Full Road Closure · Monday & Tuesday

  • Douglas Ave. closed at the project site just south of Skinner Blvd. — Virginia, Monroe, and Grant Sts. stay open for local access
  • Placed on Monday and Tuesday — the quietest downtown days — in coordination with the City, avoiding Fridays and weekends entirely
  • Signed detour via Skinner Blvd., Broadway, and Main St. — see the map below
  • Pedestrian accommodation maintained with signed crossings and routing
  • Emergency services coordinated in advance · both lanes fully reopened by Wednesday morning, November 11

Detour Map — Full Closure, Nov 9–10

On Monday–Tuesday, November 9–10, Douglas Avenue closes at the project site, just south of Skinner Boulevard — the stretch between Kafe Racer at the Skinner corner and The Artisan apartments — while the crane comes down. Through traffic detours via Skinner Blvd., Broadway, and Main Street in both directions. Virginia, Monroe, and Grant Streets stay open, and local access is maintained on Douglas from both directions right up to the barricades, including resident access to The Artisan. Pedestrians are routed with signed crossings. Every business on Douglas Avenue remains reachable on both days.

N BROADWAY SKINNER BLVD (SR 580) MAIN STREET ← TO DOWNTOWN & MARINA GRANT ST MONROE ST VIRGINIA ST open — local access PINELLAS TRAIL — OPEN DOUGLAS AVE DOUGLAS AVE ROAD CLOSED · NOV 9–10 KAFE RACER DOUGLAS PARKING CENTER 968 Douglas THE ARTISAN APARTMENTS ← DETOUR (THRU TRAFFIC)
  • Douglas Ave. closed at the project site, just south of Skinner Blvd. — Monday Nov 9 and Tuesday Nov 10 only
  • Detour: Skinner Blvd. → Broadway → Main St. (both directions)
  • Open roads — Virginia, Monroe, and Grant Sts. remain open; local access maintained up to the barricades
  • Pinellas Trail — open throughout, with protective fencing at the site

Schematic — not to scale. Route per the draft traffic control plan by Spartan Safety Services (rev. 7/29/26), pending City of Dunedin approval. The official signed detour posted in the field governs; if signage differs from this map, follow the signs. Both lanes reopen by Wednesday morning, November 11.

How the pieces get here

Deliveries, One Truck at a Time

Every precast component travels a single, pre-validated route — physically test-driven with a loaded transport in July 2026 and coordinated with FDOT District Seven and Pinellas County. Deliveries arrive individually on a scheduled cadence, never in convoys, so trucks don't queue on public streets.

  • US 19 North — oversized loads leave the highway at Sunset Point Road
  • Sunset Point Road west to Keene Road
  • Keene Road to Union Street
  • Union Street to Douglas Avenue
  • Douglas Avenue south to the project site at 968 Douglas Ave.

Daily Work Hours

7:00 AM – 5:00 PM. All precast delivery trucks are done for the day by 3:00 PM — no oversized loads on local roads during afternoon school pickup or the evening commute. No deliveries on Saturdays or Sundays, ever — weekend events downtown, including the October 10–11 Art & Craft festival, see no construction traffic.

The Pinellas Trail Stays Open

The site's western edge runs along the Pinellas Trail. Trail access and the existing trail connection are maintained throughout construction, with protective fencing separating trail users from the work. No crane picks will be made over the trail while it's open to the public.

Traffic Control You Can See

All temporary traffic control follows FDOT Design Standards and the MUTCD: advance warning signs ahead of the work zone, variable message boards before each closure window, certified flagmen, and daily inspection of every device for the duration of any closure.

What we're building

A Public Parking Garage for Downtown Dunedin

The Douglas Parking Center is a four-story public parking garage rising at 968 Douglas Avenue — a total-precast concrete structure manufactured by Metromont and erected by Hawkins Construction, with ground-floor space reserved for a future phase of downtown activity.

309
Public parking spaces
4
Stories of precast concrete
±30,000 SF
Street-level space for future retail & entertainment (pending rezoning)
8 wks
Erection window — 5½ of them with zero road impact

Aerial flyover of the completed project (49 seconds).

The bigger picture

Phase 1 of a Larger Investment in Downtown

The Douglas Parking Center is the first phase of a two-phase, family-led investment in downtown Dunedin — built first, on purpose, so the parking arrives before everything else does. Phase 2, the Main Street Exchange, follows just down the block at 830 Douglas Avenue — a short walk south along Douglas at the corner of Main Street.

Phase 1 · Douglas Parking Center

968 Douglas Avenue

  • 309 covered public parking spaces serving downtown, local businesses, and events
  • ±30,000 SF of street-level space planned for future retail and family entertainment (pending rezoning)
  • Direct walking access to the Pinellas Trail
  • Overall completion targeted for the first quarter of 2027

Phase 2 · Main Street Exchange

830 Douglas Avenue

  • 89-room boutique hotel with a rooftop terrace and bar
  • Food hall & marketplace featuring local operators, plus a 280-seat theater and event venue
  • Speakeasy, signature restaurant, small-format retail, and public green spaces
  • Unanimously approved by the City Commission · projected opening 2029

Full project details, renderings, and FAQs live at mazasdevelopment.com/mse — where you can also take the community survey and join the project mailing list for updates.

Contact us

Have a Question? Ask Us Here.

Whether you live or run a business on Douglas Avenue, have a question about a closure date, or just want to know more about the project, send it through and we’ll get back to you. Every message goes straight to the project team.

By submitting, you acknowledge and agree that all feedback, ideas and suggestions submitted through this site become the property of Mazas Development and may be used in future project planning, communications or activations without compensation.

Owner / Developer
Mazas Development LLC · 811 Douglas Avenue, Dunedin, FL 34698 · (727) 205-4700
General Contractor
Hawkins Construction, Inc. — Eric Brooks, Site Superintendent · (727) 946-2253