The dates below are from the Hawkins Construction erection sequence issued by the precast erector in October 2026, — the current working schedule for the job. If weather or logistics move a closure date, this page is updated and the City of Dunedin is notified before any closure begins.
No road or lane closure
Tue Sep 8 – Wed Sep 9, 2026 · 2 days
Crane Mobilization & Assembly
The erection crane moves to the job site and is assembled entirely within the property. Certified flaggers at the site entrance will briefly hold traffic only while a truck is actually turning in or out. Both lanes of Douglas Avenue stay open.
No road or lane closure
Thu Sep 10 – Fri Oct 30, 2026 · underway now
West & Center Bays — North to South
Erection begins September 10, building the West and Center bays — the two farthest from the road — north to south. The crane and all delivery trucks operate inside the property limits — both lanes of Douglas Avenue remain open for this entire stretch, the longest phase of the job. All work runs Monday through Friday — no weekend activity, and no precast deliveries on Saturdays or Sundays at any point in the program.
Single-lane flagging operation
Mon Nov 2 – Wed Nov 18, 2026 · about 13 working days
East Bay (Douglas Frontage) — North to South
The final bay sits along Douglas Avenue, so the crane needs the near lane. Barricades shift out to close one lane, and traffic alternates through the remaining 11-foot lane under certified flaggers — the road stays open in both directions, with brief waits during active picks, deliveries, and concrete pours. The closure runs about thirteen working days, Monday through Friday only, and the lane is restored as soon as the frontage bay is complete. Work zone speed is 15 MPH, the sidewalk on the project side closes with marked crossings to the east side, and all deliveries end by 3:00 PM daily.
Full closure — two days
Thu Nov 19 – Fri Nov 20, 2026 · dates being coordinated with the City
Crane Demobilization
Taking the crane down requires the full width of Douglas Avenue for public safety — the only full closure of the entire project, scheduled for two days midweek. A signed detour routes traffic via Skinner Blvd., Broadway, and Main Street (see map below), pedestrian routing is maintained, and emergency services are coordinated in advance. The exact two-day window is being coordinated with the City, and both lanes reopen as soon as the crane is clear.
Fri Nov 20, 2026 — Precast erection complete · All lanes restored